Description
Used water from households, industries and commercial premises island-wide is collected and conveyed via an extensive sewerage reticulation system located underground for treatment at water reclamation plants (WRPs). Over time, these sewers may suffer damage from wear and tear, ground movement, tree root intrusion, etc. When this happens, used water may leak from the sewers and pollute waterways, canals and reservoirs. Therefore regular sewer rehabilitation and replacement works are needed.
Category
Sewerage (new sewer and sewer rehabilitation)
Contractor's Public Relations Officer
Ms Truya Marijoy Millones ( 82579355 )
Contractor
Presscrete Engineering Pte Ltd
Consultant
CKMbT International Pte Ltd
Duration
1st Quarter - 2017 to 3rd Quarter - 2022
PUB Project Officer
Jenny Lau Yen Chuin ( 94528036 )
Second PUB Project Officer