Number
1190358
Title
Rehabilitation of Sewerage Network Phase 5 – Southern Region Contract 1
Description
Used water from households, industries and commercial premises island-wide is collected and conveyed via an extensive sewerage reticulation system located underground for treatment at water reclamation plants (WRPs). Over time, these sewers may suffer damage from wear and tear, ground movement, tree root intrusion, etc. When this happens, used water may leak from the sewers and pollute waterways, canals and reservoirs. Therefore regular sewer rehabilitation and replacement works are needed.
Category
Sewerage (new sewer and sewer rehabilitation)
Contractor's Public Relations Officer
Alvin Lo ( 94599311 )
Contractor
O Liner Technology Pte Ltd
Consultant
CH2M Hill Singapore Pte Ltd
Duration
3rd Quarter - 2019 to 1st Quarter - 2022
PUB Project Officer
Daphne CHEN ( 87555289 )
Second PUB Project Officer
Mohd Faruq ( 88286019 )