Number
1140278
Title
Construction of Stamford Diversion Canal Contract 1 - Tanglin and Kim Seng
Purpose of project
The Stamford Diversion Canal, together with the Stamford Detention Tank, is part of a holistic “source-pathway-receptor” approach to strengthen flood protection for the Stamford Canal Catchment, which covers the Orchard Road shopping belt.
Scope of work
The new 2km-long diversion canal will run underneath the road, from Tanglin along Grange Road, across Hoot Kiam Road, through Irwell Bank Road, River Valley Road, off Kim Seng Road, and to the Singapore River. Connecting the upstream section of Stamford Canal to the Singapore River, the diversion canal will be 6m to 14m wide and 3m to 4m deep. Stormwater from the upstream section of Stamford Canal catchment will flow into the new diversion canal towards Singapore River and eventually into the Marina Reservoir.
Current update on progress
Work commenced in Q3 2014 and will complete by Q3 2018.
Press Release
-
Project Category
Drainage (Drainage Upgrading Programme)
Contractor’s Public Relations Officer
( )
Contractor
Or Kim Peow Contractors (Pte) Ltd
Consultant
CPG Consultants Pte Ltd
Duration
3rd Quarter - 2014 to 3rd Quarter - 2018
PUB Project Officer
Ng Rui Qiang ( 97882857 )
Second PUB Project Officer
Ahmad Zaki Bin Salleh ( 90035844 )