Number
1220443
Title
Proposed Twin 1800mm Diameter Water Pipelines from Island Club Road to Upper Thomson Road
Purpose of project
The project is to lay a twin 1800mm diameter meter potable water transmission pipelines to meet the increasing demand in North East areas of Singapore.
Scope of work
Supply and installation of approximately 5.4km of 1800mm diameter potable water (PW) transmission pipelines by pipe jacking and open cut method from Island Club Road to Upper Thomson Road
Current update on progress
Shaft construction and pipe jacking works in progress.
Project Category
Water Supply (NEWater, potable water)
Contractor’s Public Relations Officer
Gan Sha Kee ( 91281983 )
Contractor
Ah Boon Civil Engineering & Building Contractor Pte Ltd
Consultant
AECOM Singapore Pte Ltd
Duration
2nd Quarter - 2023 to 4th Quarter - 2026
PUB Project Officer
Jacqueline Ong ( 91913725 )
Second PUB Project Officer
Kenneth Way Kai Wei ( 90045608 )