Number
1170096
Title
Supply and Laying of 900mm/1200mm/1400mm dia Water Pipelines in Bukit Kalang Service Reservoir
Purpose of project
To augment the two existing outlet pipelines to convey more water from BKSR to the demand centres in the supply zone.
Scope of work
Pipe jacking and open trench pipe laying
Current update on progress
Open cut pipe laying has been progressing and is about 60m / 240m. Jacking shaft is completed, pipe jacking system installation is currently in progress. The receiving shaft is still under construction.
Project Category
Water Supply (NEWater, potable water)
Contractor’s Public Relations Officer
( )
Contractor
Shingda Construction Pte Ltd
Consultant
CPG Consultants Pte Ltd
Duration
1st Quarter - 2017 to 4th Quarter - 2019
PUB Project Officer
Kwan Hui Yi ( 91869809 )
Second PUB Project Officer
Tan Bo Rui ( 96428718 )